S-3.1.01, r. 1 - Dam Safety Regulation

Full text
52. The description of the remedial work that the dam owner intends to carry out to make the dam safe in accordance with good practice and the minimum safety standards, together with the implementation schedule forwarded by the owner pursuant to section 17 of the Act, must be sent to the Minister for approval at the same time as the report on the dam safety review.
The Minister’s decision under section 17 concerning the remedial work that the owner intends to carry out and of the implementation schedule must be rendered within 6 months from the date on which the file on the safety review and the application for approval of the description of remedial work and the implementation schedule is complete.
O.C. 300-2002, s. 52; O.C. 901-2014, s. 17; O.C. 989-2023, s. 39.
52. The Minister’s decision under section 17 of the Act in respect of the remedial work that the owner intends to carry out and implementation schedule must be rendered within 6 months after receipt of the outline and schedule submitted by the owner.
O.C. 300-2002, s. 52; O.C. 901-2014, s. 17.
52. The Minister’s decision under section 17 of the Act in respect of an owner’s planned remedial measures and implementation schedule must be rendered within 6 months after receipt of the outline and schedule submitted by the owner.
O.C. 300-2002, s. 52.